Cape Wind Statement on DOE $150 million Conditional Commitment

July 1, 2014

"Today's announcement by the Department of Energy represents an important endorsement by the United States government of the environmental, economic and energy benefits that offshore wind will provide to our country. We appreciate Energy Secretary Moniz helping launch the American offshore wind industry, creating jobs and unleashing a new clean energy source for the nation."  

-- Cape Wind President Jim Gordon

Cape Wind Completing Geophysical Surveys; Aided by Four Massachusetts Companies

May 12, 2014     

BOSTON, MA – Cape Wind has today announced that a team including three companies based in New Bedford, Massachusetts, is involved with completing geophysical surveys of the project site and offshore cable routes.

Survey vessels with a suite of geophysical instruments are surveying the seafloor and subsea geology on Horseshoe Shoal and along the offshore cable route. 

Federal Judge Dismisses Lawsuit against Cape Wind

Cape Wind News Release

Federal Judge Dismisses Lawsuit that Challenged Cape Wind

Suit on NSTAR Power Purchase Agreement Becomes 26th Failed Legal Attempt of Project Opponents

May 3, 2014       

Cape Wind Wins Major Legal Victories

March 14, 2014 

BOSTON, MA – In a set of major legal victories for the Federal Government and for Cape Wind, United States District Judge Reggie B. Walton today issued rulings against project opponents in their four lawsuits that had challenged Cape Wind’s permitting approval by the U.S. Department of Interior.

Cape Wind Signs Major Cables Contracts

BOSTON, MA, March 13, 2014 – Cape Wind announced today that South Carolina-based Prysmian Cables and Systems USA has been awarded the contract for the eventual supply of the intra array and export power cables for Cape Wind’s offshore wind farm and New Jersey-based Caldwell Marine International has been awarded the contract for the installation of the underwater cables.  The new contracts mark significant project milestones.

Court Upholds FAA Approval

Clean Energy Future Moves Closer -- Legal Victory for Cape Wind, FAA Approval Upheld

January 22, 2014              

BOSTON, MA – Cape Wind today again defeated the efforts of its opponents to block the country’s first offshore wind farm.  In a significant decision, the U.S. Court of Appeals for the District of Columbia Circuit upheld the FAA’s approval of the Cape Wind project, rejecting every argument that had been advanced by the project’s opponents.

Cape Wind Signs $15 Million Contract with Cape Cod Construction Contractor, Lawrence-Lynch Corp.

BOSTON, MA – Cape Wind has signed a $15 Million contract with Falmouth-based Lawrence-Lynch Corp. to provide the upland construction work required to bury Cape Wind’s electric cables.  Lawrence-Lynch Corp. will also be responsible for providing a conduit for connecting the buried electric cables on land to the submerged ocean submarine cables by using a ‘directional drill’ from the landfall point in West Yarmouth out to a temporary cofferdam they will construct in Lewis Bay.